Project Schedule
Planning and Design Phase
Concept Development: January - April 2012
- Site plan development and General Massing
- Studies: Geotech, Environmental, Traffic, Parking, Historic
- Refine Programming and Establish Budget
- Concept Submission
Schematic Design: April - September 2012
- Finalize Programming and Refine Floor Plans
- Evaluate Building Systems and Architecture
- BAR Concept Reviews
- Retain Construction Manager
- Evaluate Projected Costs, Refine Budget, and Modify Design
- Preliminary Site Plan Submission
Design Development: September - December 2012
- Finalize Building Systems, Floor Plans, and Architecture
- Detailed Cost Estimates and Related Design Modifications
- City Council Approval
- BAR Approval
Construction Documents: January - April 2013
- Final Site Plan Reviews and Building Permits