• January-March 2020: HVAC Replacement

    HVAC (Design) Status: Initiation 

    This project will replace the HVAC system in the school that is currently aged and requires replacement. 

    • Progress through Q3: Coordinated assessment of the multi-stack system and scoped replacement of compressors with Operations & Maintenance. 
    • Anticipated progress through Q4: Compressors will be replaced in Q4. Also, a design will be initiated for the replacement of the multi-stack unit and VAV boxes for 2021. 

    Read the Quarter 3 report.

    Total system wide funds spent on facilit projects for Samuel W. Tucker Elementary School between July through September 2019: $86,500.

    The system wide money was uesd to update the sports fields.