April 10, 2019 - Playground Updates

James Polk playground project commenced on April 4th, 2019. Installation of perimeter safety fencing, equipment staging and demolition was completed the week of April 8th. Installation of the new playground components began a few days ago and will continue into spring break. Curbing around the entire playground will also be completed over break. The poured-in-place rubber surface will commence towards the end of next week but will need good weather for curing. The entire project should be complete by April 25th.