  1. Schedule: Keller’s requested a schedule completion delay for Phase 2 due to weather and utilities (Dominion’s delay on providing the permanent electrical service permanent power and gas) moving substantial completion from 12/18/18 to 12/28/18. ACPS is adjusting the school’s move-in occupancy date to January 22, 2019.

  2. Revised Temporary Sidewalks and Fencing: ACPS identified adjustments that have to be made to the approved temporary sidewalks and safety separations for the construction site during Phase 3 demolition and site completion. Keller is evaluating cost implications. A final pedestrian and vehicular traffic plan will be shared in a December 2018 public meeting – yet to be scheduled.