Construction Update: May 31, 2022 -  June 14, 2022

Construction Update: May 31, 2022 -  June 14, 2022

Public utilities work is continuing on-site and the public space permit has been extended from June 1, 2022 to July 29, 2022. The affected sidewalks have been closed, and a temporary crosswalk and alternate pedestrian routes have been established. Once the work is complete and driven fence posts are installed, Skanska will open up the sidewalk for public use. The following activities are ongoing at the site:

  • Installation of the duct bank
  • Onsite storm and sanitary installation
  • Underground mechanical, electrical and plumbing installation
  • A grease interceptor is to be installed in the garage this week.
  • Spray foam has started in the garage
  • Sidewalk and curb installation
  • Mockup of the façade construction at the southeast corner of the site
  • Stair B masonry construction
  • Construction of the garage ramp retaining wall
  • Learning Stair Concrete construction

Structural steel construction is ongoing. The crane will be on-site through the end of July for structural steel erection.